A certificate of occupancy, or CO, is a document issued by the local building authority stating that a building can be legally occupied or used. New York City's Department of Buildings says a CO states a legal use and type of permitted occupancy, and new buildings must have one. The Florida Building Code, §111, says no building may be used or occupied until the building official issues a CO.
Updated November 19, 2026
A certificate of occupancy, or CO, is a document from the local building authority stating that a building may be legally occupied and used. New buildings generally need one before anyone can move in, and buyers should ask for it on new construction and major renovations.
What it is, with examples
New York City's Department of Buildings says a CO states a legal use and type of permitted occupancy of a building; new buildings must have one, and existing buildings need a current or amended one when use, egress or occupancy type changes. Its code notes say a CO confirms completed work complies with applicable laws, the paperwork and fees are done and relevant violations are resolved. The department issues a final CO when the completed work substantially conforms to the approved plans.
In Florida, the Florida Building Code, §111, states that no building or structure shall be used or occupied until the building official has issued a certificate of occupancy. After inspecting the building and not finding violations, the building official issues the CO, and may issue a temporary certificate of occupancy for a portion of the work when that portion can be occupied safely (§§111.1 to 111.3). Local building departments administer the code. A Florida city building department explains that once inspections are made and the construction is found to comply with applicable codes, the department issues the CO.
Why buyers should care
- Legal occupancy: without one, living in a new building may not be permitted.
- Financing and closing: lenders and contracts may require the CO or a temporary one; ask yours.
- Warranties: in Florida's condominium statute, completion for warranty purposes means a certificate of occupancy that allows occupancy or use of the entire building (§ 718.203(3)).
- Renovations and additions: a new CO or amended CO may be needed when use or occupancy changes.
What to ask for
- A copy of the current CO, and the permit history for the property.
- For new construction, confirmation of when the CO is expected and what remains open.
- For older buildings, ask how the jurisdiction records legal use; NYC notes that a Letter of No Objection may confirm legal use for buildings built before 1938 when no CO was required.
- For additions or conversions, evidence that work was permitted and closed out.
Rules differ by city and state, so ask your attorney and the local building department what applies.
Sources
- NYC Department of Buildings, Temporary Certificate of Occupancy
- NYC Department of Buildings, Code Notes: Certificate of Occupancy and Temporary Certificate of Occupancy
- Florida Building Code, Building, 8th Edition (2023), § 111, Certificate of Occupancy
- Florida Building Commission, 8th Edition (2023) Florida Building Code, Building, Chapter 1 (Section 111 text as hosted)
- City of Titusville, Florida, Certificates of Occupancy
- Fla. Stat. § 718.203, Warranties (2026)
Related: What Is a TCO vs CO? and What Is a Punch List?.
This is general information from Haute Real Estate Network, not legal, tax or financial advice.
Frequently Asked Questions
Does every house have a certificate of occupancy?
Not necessarily. Older buildings may predate CO requirements, and rules vary by place. NYC, for example, may issue a Letter of No Objection for some pre-1938 buildings.
Who issues the CO?
The local building department or authority.
Do I need one on an existing home I am buying?
Ask your attorney. Requirements vary by location and transaction.